How are landfills constructed?
Under the waste:
- The existing sub grade is excavated to create a solid base for the waste.
- The liners are installed.
- Three foot layer of recompacted clay.
- Sixty mil thick synthetic Plastic 2 liner.
- Leachate collection system (either granular material or geocomposite).
- Protective layer (typically sand).
- Layer of select waste.
- *Daily cover which is a 6 inch dirt layer or a specifically designed tarp.
*Unless the facility is open 24 hours.
On top of the waste-the Final Cap
- Six inches of daily cover.
- One foot layer of intermediate cover soil.
- Eighteen inches of re-compacted soil
- Sixty mil thick synthetic Plastic 2 liner.
- Two and a half feet of protective/vegetative soil and grass.